Design - Equipment finishes
Provenance
1 result
Fields:
| Fact | Field | Value | Latest Entry Date | |
|---|---|---|---|---|
| 5e1ca8ae490aa5cc6c728c44ac1d90b4f3d3b150755a1e277936c62d4f4b2597 | description | Prior to the construction or installation of the respective structures identified below, the following details shall first be submitted to, and agreed in writing by, the Local planning Authority: Details of the colour and finish of the GIS hall building. Details of the colour and finish of the energy storage containers. Details of the colour and finish of the water containers. Details of the colour and finish of the DNO substation building. Details of the colour and finish of the perimeter fence. Details including design, height, colour and finish of site access gate. The development shall then be constructed in accordance with the approved details and shall be retained and maintained as such at all times. | 2025-06-21 |