5db244383f7ab97774473518b5742d3026610bd05227442bcadd94667582063e description The development hereby approved shall be carried out in accordance with the submitted flood risk assessment (ref. JOC Consultants Ltd, ref. 23/023.01 Revision 01, dated 8th November 2023) and the finished floor levels it contains at paragraph 8.1.2. These mitigation measures shall be fully implemented prior to occupation and subsequently in accordance with the scheme's timing/ phasing arrangements. The measures detailed above shall be retained and maintained thereafter throughout the lifetime of the development. 2025-06-21