FRA Compliance
Provenance
1 result
Fields:
| Fact | Field | Value | Latest Entry Date | |
|---|---|---|---|---|
| e342fdac37d795ecd0bf875e2273b6747a7d82c897b95c738686f29017df31c9 | description | The development shall be carried out in accordance with the submitted flood risk assessment (ref 81086R1, dated 12th January 2024 and compiled by GeoSmart Information Ltd.) and the following mitigation measures it details: - Finished floor levels shall be set no lower than 4.4 metres above Ordnance Datum (AOD), as detailed within Section 7 of the report. - Additional flood resilience measures identified within Section 7 of the report. These mitigation measures shall be fully implemented prior to occupation and subsequently in accordance with the scheme's timing/phasing arrangements. The measures detailed above shall be retained and maintained thereafter throughout the lifetime of the development. | 2025-06-21 |