Planning Ref: 09/01021/FULMAJ.The conversion of Bank Hall into 12 dwellings has started. The 23 new build dwellings are expected to commence following completion of the conversion. It is predicted that all of these dwellings will be completed in the five year period.. Refurbishment of Bank Hall into 12 dwellings. Enabling development is the erection of 23 dwellings on the former orchard site but this is not on brownfield land.
|