NEW LAA ref CCB8. Supersedes previous prior notification MC/17/3238. MC/22/1286 conditions 30 and 31. MC/22/2176 non material amendment to condition 15 wording. MC/21/2463 condition 11, MC221286 conditions 30 and 31, MC222176 amendment to condition 15 wording, MC222829 condition 10, MC231218 condition 11 and MC231534 conds 4,6,9 discharged, MC232745 conditions 12,41,42 discharged, MC240008 variation of conditions 3,22,1,18,20 and 19 and MC242164 conditins 42 discharged. Decision awaited on MC241909 condition 17. Piling complete, commencement of building works expected April 2025.
|