Value Redevelopment of former hospital site for 375 dwellings underway and due to completed in 2024/25 (14/02750/FUL). Part brownfield and part greenfield land. Brownfield element (c.6ha) represents around one-third of the site area - a yield of around 124 dwellings can be calculated based on methodological approach. For indicative purposes in the BF Register, the original SHLAA site (ref 3397) is split to reflect brownfield and greenfield elements - total area of 19.8ha. Alongside the residential development, the scheme also includes a wide variety of supporting infrastructure, services and facilities.
Entity 3397x
Earliest entry date 2019-12-17
Latest entry date 2019-12-17
Latest resource 861b110ca9fb6ce201b997d8c904056946a15f6e596400415558060fc0a7699a
Resources
Entry Date Resource
2019-12-17 861b110ca9fb6ce201b997d8c904056946a15f6e596400415558060fc0a7699a