[{"fact":"1fdc2f3a0fd889fbc0b105cb3fffe40f83c76ca964a285fcaf3271ff9f9c1e73","entity":73002775,"reference-entity":"","field":"description","value":"No development shall take place, including any works of demolition, until a Construction Method Statement has been submitted to and approved in writing by the local planning authority. The approved statement shall be adhered to throughout the construction period. The statement shall provide for: i. the site compound and parking of vehicles for site operatives and visitors ii. the erection and maintenance of security hoarding for the compound, if appropriate iii. Size, routing and numbers of abnormal loads with swept path analysis (as required) iv. the areas for loading and unloading of these materials even outside the prison if not being delivered directly into it. v. storage of plant and materials used in constructing the development if not being stored within the prison vi. wheel washing facilities unless all areas of construction are within existing hard standing areas","entity-name":"CMS","entity-prefix":"planning-condition","entity-reference":"U0121818","earliest-entry-date":"2025-02-25","latest-entry-date":"2025-06-21","latest-resource":"cddbf6b3b9eea723b5249c68a38910c2e0b5179b9d93e006eb17572584b10bdc","resources":""}]