[{"fact":"92aa0dfa5a0ac5c4380c7e19e149feaca70eefef5e859c1aaea5cbb37894b6f4","entity":73002764,"reference-entity":"","field":"description","value":"The development shall be carried out in accordance with the submitted flood risk assessment Flood Risk Assessment by Eastwood Consulting Engineers, referenced 47920, Issue 4, dated 19 March 2024, and the following mitigation measures it details: o Finished floor levels of the battery storage containers, control and transformers shall be set no lower than a minimum of 600mm above adjacent ground levels. o As per Section 2.1.1, in the event of a breach of the main river defences, flood waters will be allowed to enter the site. These mitigation measures shall be fully implemented prior to occupation and subsequently in accordance with the scheme's timing/phasing arrangements. The measures detailed above shall be retained and maintained thereafter throughout the lifetime of the development.","entity-name":"FRA","entity-prefix":"planning-condition","entity-reference":"U0121633","earliest-entry-date":"2025-02-25","latest-entry-date":"2025-06-21","latest-resource":"cddbf6b3b9eea723b5249c68a38910c2e0b5179b9d93e006eb17572584b10bdc","resources":""}]