Skip to main content

This is a new service - your feedback will help us to improve it.

Search for planning and housing data

Warning The data may be incomplete and not yet cover all of England. We're working to improve its availability and quality.

Filters

Typology

Typology

Dataset

1 selected
Dataset

Location

Location

Organisation

Organisation

Period

Period

Entry date

Which date are you interested in?
For example, 27 3 2021
Do you want to see entries since the date or after the date?
Clear

5,605 results

  • Typology type: Policy

    U0124931

    Approval of details - removed

    Removed.

    Reference
    U0124931
  • Typology type: Policy

    U0124932

    Approved plans

    The development hereby permitted must be carried out and completed entirely in accordance with the terms of this permission and the details shown on the approved plans listed below: Location plan received 20.11.23 Proposed Site Plan dated 15 November 2023 received 16.11.23 Gomde UK_Temple elevation 01 South received 12.06.24 UK_Temple elevation 02 West-East received 12.06.24 Gomde UK_Temple elevation 03 North received 12.06.24 Temple_00 Basement plan received 12.06.24 Temple_01 Ground floor plan received 12.06.24 Temple_02 1st floor plan received 12.06.24 Temple_03 2nd floor plan received 12.06.24 Temple_04 3rd floor plan - roof received 12.06.24 Temple_section 01 A-A_A2 received 12.06.24 Temple_section 02 B-B_A2 received 12.06.24 Temple_section 03 C-C received 12.06.24 Temple_Main facade_Decoration principles received 12.06.24 Limestone blocking and window brow received 15.05.24 Surface water details May 2024 received 12.06.24 Pond maintenance received 16.11.23 Facade and Sections 01 received 16.11.23 Facade and Sections 02 received 16.11.23 Facade and Sections 03 received 16.11.23 Ground Floor Plan received 16.11.23 First Floor Plan received 16.11.23 Second Floor Plan received 16.11.23 Info and Shop Plans, Facade and Section received 16.11.23 Lindholme Hall Workshop received 16.11.23

    Reference
    U0124932
  • Typology type: Policy

    U0124933

    Passing places

    The passing places as shown on the approved drawings 'Highway Passing Places Locations' and 'Highway Widening Details' shall be implemented in accordance with the agreed details prior to occupation of any part of the development on the site.

    Reference
    U0124933
  • Typology type: Policy

    U0124934

    CON1 minus part A

    No development approved by this permission shall be commenced prior to a contaminated land assessment and associated remedial strategy, together with a timetable of works, being accepted and approved by the Local Planning Authority (LPA), unless otherwise approved in writing with the LPA. b) The Phase 2 site investigation and risk assessment, if appropriate, must be approved by the LPA prior to investigations commencing on site. The Phase 2 investigation shall include relevant soil, soil gas, surface and groundwater sampling and shall be carried out by a suitably qualified and accredited consultant/contractor in accordance with a quality assured sampling and analysis methodology and current best practice. All the investigative works and sampling on site, together with the results of analysis, and risk assessment to any receptors shall be submitted to the LPA for approval. c) If as a consequence of the Phase 2 Site investigation a Phase 3 remediation report is required, then this shall be approved by the LPA prior to any remediation commencing on site. The works shall be of such a nature as to render harmless the identified contamination given the proposed end-use of the site and surrounding environment including any controlled waters, the site must not qualify as contaminated land under Part 2A of the Environment Protection Act 1990 in relation to the intended use of the land after remediation. d) The approved Phase 3 remediation works shall be carried out in full on site under a quality assurance scheme to demonstrate compliance with the proposed methodology and best practice guidance. The LPA must be given two weeks written notification of commencement of the remediation scheme works. If during the works, contamination is encountered which has not previously been identified, then all associated works shall cease until the additional contamination is fully assessed and an appropriate remediation scheme approved by the LPA. e) Upon completion of the Phase 3 works, a Phase 4 verification report shall be submitted to and approved by the LPA. The verification report shall include details of the remediation works and quality assurance certificates to show that the works have been carried out in full accordance with the approved methodology. Details of any post-remedial sampling and analysis to show the site has reached the required clean-up criteria shall be included in the verification report together with the necessary documentation detailing what waste materials have been removed from the site. The site shall not be brought into use until such time as all verification data has been approved by the LPA.

    Reference
    U0124934
  • Typology type: Policy

    U0124935

    Phasing - updated

    The phasing for the development shall be carried out in accordance with the submitted Phased Order of Works Courtyard and Temple Development document submitted 12 June 2024.

    Reference
    U0124935
  • Typology type: Policy

    U0124936

    Tree protection

    The layout of the proposed development shall be based on the need to retain all sound and healthy trees within the site and the siting of any proposed development shall be based on the 'Lindholme Hall Site Plan - Proposed; ref. paperformat A2 dated 03.12.2015. Prior to the commencement of the development a pre-commencement meeting shall be undertaken to ensure that a scheme for the protection of all retained trees that complies with section 6.2 of British Standard 5837: 2012 Trees in Relation to Design, Demolition and Construction - Recommendations is installed to the satisfaction of the Local Planning Authority. Thereafter, all tree protection shall be maintained in full accordance with the approved details until all equipment, machinery and surplus materials have been removed from the site, unless the local planning authority gives its written approval to any variation. Nothing shall be stored or placed in any area fenced in accordance with this condition and the ground levels within those areas shall not be altered, nor shall any excavation be made, without the written consent of the Local Planning Authority.

    Reference
    U0124936
  • Typology type: Policy

    U0124937

    WSI

    The development shall only take place in accordance with the approved WSI. Prior to commencement of the relevant works as set out in the recommendations of the WSI, the applicant shall contact South Yorkshire Archaeological Service to agree an approved scheme of works. A final report shall be submitted to and approved in writing by the Local Planning Authority. The development shall be carried out in accordance with the agreed recommendations.

    Reference
    U0124937
  • Typology type: Policy

    U0124938

    CEMP and EEP

    The approved CEMP shall be adhered to and implemented throughout the construction period strictly in accordance with the approved details, unless otherwise agreed in writing by the local planning authority.

    Reference
    U0124938
  • Typology type: Policy

    U0124939

    FRA

    The development permitted by this planning permission shall be carried out in accordance with the approved flood risk assessment (FRA) produced by Rangjung Yeshe UK and the following mitigation measures detailed within the FRA: 1. Check and review the registration to Environment Agency Floodline Warnings Direct service. 2. Carry out a regular review of the 'islanding plan'. The mitigation measures shall be fully implemented prior to occupation and subsequently in accordance with the timing / phasing arrangements embodied within the scheme, or within any other period as may subsequently be agreed, in writing, by the local planning authority.

    Reference
    U0124939
  • Typology type: Policy

    U0124940

    EEP

    The approved ecological enhancement plan shall be adhered to and implemented strictly in accordance with the approved details, unless otherwise agreed in writing by the local planning authority. Upon completion of the scheme, a report shall be produced with evidence to demonstrate that the recommendations have been implemented in accordance with the agreed details.

    Reference